# New submarine pier ready in Karlskrona

- Source: Nordic Defence Sector (https://nordicdefencesector.com)
- Canonical URL: https://nordicdefencesector.com/en/article/new-submarine-spire-ready-in-karlskrona
- Published: 2026-05-04
- Author: Johan Martelius
- Type: News · Section: Maritime · Country: sweden
- Language: en — machine translation from sv; the sv version is authoritative: https://nordicdefencesector.com/sv/article/new-submarine-spire-ready-in-karlskrona.md
- Also available in: de (https://nordicdefencesector.com/de/article/new-submarine-spire-ready-in-karlskrona.md), dk (https://nordicdefencesector.com/dk/article/new-submarine-spire-ready-in-karlskrona.md), es (https://nordicdefencesector.com/es/article/new-submarine-spire-ready-in-karlskrona.md), fi (https://nordicdefencesector.com/fi/article/new-submarine-spire-ready-in-karlskrona.md), fr (https://nordicdefencesector.com/fr/article/new-submarine-spire-ready-in-karlskrona.md), it (https://nordicdefencesector.com/it/article/new-submarine-spire-ready-in-karlskrona.md), no (https://nordicdefencesector.com/no/article/new-submarine-spire-ready-in-karlskrona.md), pl (https://nordicdefencesector.com/pl/article/new-submarine-spire-ready-in-karlskrona.md)
- Primary source: https://www.fortifikationsverket.se/arkiv/nyheter/2026/2026-04-27-ny-ubatspir-invigd-i-karlskrona
- Tags: försvarsmakten, fortifikationsverket, karlskrona, swedish navy, naval base, submarine pier

> The Fortifications Agency has handed over a new submarine pier in Karlskrona naval harbour to the Swedish Armed Forces, six months ahead of schedule. The pier has capacity for larger submarines and a carbon footprint reduced by one third. The renovation of the harbour continues with additional sections, including the Fleet's ship bridge and the tugboat pier.

![The new submarine pier will be able to accommodate larger submarines and the quays have been given a better working environment.](https://imagedelivery.net/XO8UY-c6-LfWgEjQsN8IQw/9375713a-dabd-411c-40b4-06948c03e800/public)
*The new submarine pier will be able to accommodate larger submarines and the quays have been given a better working environment. · Anna Palm / Fortifikationsverket*

**The Swedish Fortifications Agency (Fortifikationsverket) has handed over the first phase of the renovation and expansion of the naval base in Karlskrona (southern Sweden) to the Swedish Armed Forces (Försvarsmakten). The new submarine pier is complete and will be able to accommodate larger submarines.**

Work began in autumn 2024 and also encompasses the refurbishment of quays that had reached the end of their technical service life. The quays have been adapted for increased operational activity and climate-proofed against rising sea levels.

– This is a very successful project, where the key to success, as so often, is collaboration. The Swedish Fortifications Agency faces several harbour renovations ahead, and we will carry the lessons learned from this project forward, says Ulrika Hörgren, Project Director at the Swedish Fortifications Agency, in a [press release](https://www.fortifikationsverket.se/arkiv/nyheter/2026/2026-04-27-ny-ubatspir-invigd-i-karlskrona).

The project was completed six months ahead of schedule. According to the Swedish Fortifications Agency, the carbon footprint has been reduced by approximately one third, partly through reduced use of concrete and materials with lower emissions.

Working conditions have also been improved, including the removal of hazardous elements associated with bunkering and gangway operations.

The renovation of the naval base now continues with additional sections, including the Fleet's ship pier and the tugboat pier.

## FAQ

**When was the new submarine pier in Karlskrona completed?**

The new submarine pier in Karlskrona was completed six months ahead of schedule. Work commenced in autumn 2024 and constitutes the first phase of the renovation and expansion of the naval harbour. The Fortifications Agency handed over the pier to the Swedish Armed Forces upon project completion. Last fact-checked: 2026-05-04.

**What has the Fortifications Agency done to reduce the carbon footprint of the submarine pier in Karlskrona?**

The Fortifications Agency reports that the carbon footprint of the submarine pier in Karlskrona has been reduced by approximately one third. This has been achieved through reduced concrete usage and selection of materials with lower emissions. The project is highlighted as an experience to carry forward to future harbour renovations. Last fact-checked: 2026-05-04.

**What additional components are included in the renovation of the naval harbour in Karlskrona?**

The renovation of the naval harbour in Karlskrona continues with additional components following the handover of the submarine pier. Among the forthcoming projects are the Fleet's ship bridge and the tugboat pier. The project also encompasses refurbishment of quays that have reached their technical service life and climate protection against rising sea levels. Last fact-checked: 2026-05-04.

---
Nordic Defence Sector — independent newsroom covering the Nordic defence sector. When citing, attribute "Nordic Defence Sector" and link https://nordicdefencesector.com/en/article/new-submarine-spire-ready-in-karlskrona. Site guide: https://nordicdefencesector.com/llms.txt