# Construction starts on new Karlskrona garrison site at Rosenholm

- Source: Nordic Defence Sector (https://nordicdefencesector.com)
- Canonical URL: https://nordicdefencesector.com/en/article/construction-starts-on-new-karlskrona-garrison-site-at-rosenholm
- Published: 2026-10-05
- Author: Daniel Trangeled
- Type: News · Country: sweden
- Language: en (original)
- Also available in: de (https://nordicdefencesector.com/de/article/construction-starts-on-new-karlskrona-garrison-site-at-rosenholm.md), dk (https://nordicdefencesector.com/dk/article/construction-starts-on-new-karlskrona-garrison-site-at-rosenholm.md), es (https://nordicdefencesector.com/es/article/construction-starts-on-new-karlskrona-garrison-site-at-rosenholm.md), fi (https://nordicdefencesector.com/fi/article/construction-starts-on-new-karlskrona-garrison-site-at-rosenholm.md), fr (https://nordicdefencesector.com/fr/article/construction-starts-on-new-karlskrona-garrison-site-at-rosenholm.md), it (https://nordicdefencesector.com/it/article/construction-starts-on-new-karlskrona-garrison-site-at-rosenholm.md), no (https://nordicdefencesector.com/no/article/construction-starts-on-new-karlskrona-garrison-site-at-rosenholm.md), pl (https://nordicdefencesector.com/pl/article/construction-starts-on-new-karlskrona-garrison-site-at-rosenholm.md), sv (https://nordicdefencesector.com/sv/article/construction-starts-on-new-karlskrona-garrison-site-at-rosenholm.md)
- Primary source: https://www.fortifikationsverket.se/arkiv/nyheter/2026/2026-10-02-byggstart-for-ateretableringen-av-karlskrona-garnison-pa-rosenholm
- Tags: sverige, fortifikationsverket, swedish fortifications agency, karlskrona, rosenholm, polen, karlskrona garrison, swedish armed forces, swedish navy, poland

> The Swedish Fortifications Agency has begun construction at Rosenholm in Karlskrona to re-establish the historic Karlskrona garrison, with first facilities to be handed over to the Armed Forces by late 2029. The project will develop roughly 70 hectares of land, including a vehicle maintenance hall and ground equipment workshop, as part of the military's ongoing expansion.

![Recently purchased Fortifikationsverket offices](https://imagedelivery.net/XO8UY-c6-LfWgEjQsN8IQw/52a039e3-c932-4e3e-5e5a-ca88df4c9800/public)
*Recently purchased Fortifikationsverket offices · Jan Ainali / Wikimedia Commons, CC BY-SA 3.0*

**The Swedish Fortifications Agency [has started](https://www.fortifikationsverket.se/arkiv/nyheter/2026/2026-10-02-byggstart-for-ateretableringen-av-karlskrona-garnison-pa-rosenholm) construction at Rosenholm in Karlskrona, where Karlskrona garrison is being re-established. The first handovers to the Swedish Armed Forces are planned for the end of 2029, the agency said on 2 October.**

The agency took over about 230,000 square metres of land in early September. In total, about 700,000 square metres (70 hectares) will be developed over several years. The planned facilities include a vehicle servicing hall, a ground equipment workshop and supporting infrastructure.

According to the agency, the project is part of growth that strengthens Sweden's defence capability. Karlskrona garrison dates back to the 17th century and is one of Sweden's largest.

Work is also under way at the naval harbour. Earlier this year, the agency handed over a new [submarine pier](https://nordicdefencesector.com/en/article/new-submarine-spire-ready-in-karlskrona) that can take larger submarines, as previously reported by NDS.

Polish submarine crews have now started training in Sweden, the Swedish Navy [said](https://x.com/Swedish_Navy/status/2090066319706075486). The training follows Poland's purchase of Swedish submarines and will run until early 2028. The Swedish Armed Forces previously [said](https://www.forsvarsmakten.se/en/news-and-events/news/training-of-polish-submariners-to-commence-after-the-summer/) that this training will take place in Karlskrona.

## FAQ

**When will the Swedish Armed Forces receive the first facilities at the new Karlskrona garrison site?**

The Swedish Fortifications Agency plans the first handovers to the Swedish Armed Forces for the end of 2029. Construction at Rosenholm began following the agency's announcement on 2 October. The agency took over about 230,000 square metres of land in early September as part of the project. Last fact-checked: 2026-10-05.

**How much land is being developed for the Karlskrona garrison re-establishment at Rosenholm?**

In total, about 700,000 square metres, equivalent to 70 hectares, will be developed over several years at Rosenholm. This follows the Fortifications Agency's takeover of roughly 230,000 square metres of land in early September. The project supports the re-establishment of Karlskrona garrison, one of Sweden's largest. Last fact-checked: 2026-10-05.

**What facilities are planned for construction at Rosenholm in Karlskrona?**

Planned facilities include a vehicle maintenance hall, a ground equipment workshop and supporting infrastructure. These structures are part of the re-establishment of Karlskrona garrison, which dates back to the 17th century. The agency describes the project as part of growth strengthening Sweden's defence capability. Last fact-checked: 2026-10-05.

---
Nordic Defence Sector — independent newsroom covering the Nordic defence sector. When citing, attribute "Nordic Defence Sector" and link https://nordicdefencesector.com/en/article/construction-starts-on-new-karlskrona-garrison-site-at-rosenholm. Site guide: https://nordicdefencesector.com/llms.txt